a. Schematic Design is 95% complete
b. Design development to commence
c. Meet with the Diocese of Dallas Building
Commission
d. Meet with the Diocese of Dallas Sacred
Places Committee
COMPLETE -
This coming week, the survey crew will stake the location for the foundation **storage container will arrive.
Close down & empty the HC.
Remove vegatation around the HC required for its relocation
The windows will be removed starting Dec. 2 and transported to the stained glass Co.'s facility for reimbursement. The windows will be replaced with plywood. Removal is estimated to take approximately 5+ days.
Remove lower skirt from the HC.
Foundation crew will stake the location for the foundation piers. Next week pier crew will drill and pour the concrete piers.
Borings under drives for utilities.
REVISIONS
Foundation Crew will excavate for the foundation and pour the concrete beams/footings - second or third week of April.
HC will be moved and set/cribbed above the beams. Third or fourth week of April.
Underground water and electric installed. Late April.
Foundation crew will install drains, pour the foundation walls then backfill fourth week of April.
HC will be lowered onto the foundation walls. First week of May.
Demolition and removal of current foundation along with backfill. First half of May.
Renovate HC.
Updates (TBA).